Behind The Build

The latest construction updates from the Westfield CC Club Master Plan. More information will be shared as key milestones are achieved. Click on the Titles below for more information.

June 09, 2025

Clubhouse Steel, Pool, Poolhouse & Retaining Walls

Clubhouse Steel, Pool Underground, Poolhouse Rough Ins, Retaining Walls and Clubhouse Backfill.

June 03, 2025

Pool House Rough Ins, Steel Progress & Retaining Wall

Pool House Rough Ins, Steel Progress and Retaining Wall.

May 27, 2025

Cart Storage, Steel & Poolhouse Trench

Cart Storage, Steel and Poolhouse Trench.

May 20, 2025

Waterproofing, CMU, Poured Walls & Wall Forms

Clubhouse Wall Waterproofing​, CMU Grout, Poured Walls, Wall Forms, and Poolhouse CMU.

May 13, 2025

Elevator, Clubhouse Walls, Interior Foundation & Poolhouse

Clubhouse Elevator, Clubhouse Walls Waterproofing, Clubhouse Interior Foundation and Poolhouse sleeves.

May 06, 2025

Clubhouse Walls & Waterproofing

Clubhouse Walls, Waterproofing, Elevator Walls and Poolhouse.