The latest construction updates from the Westfield CC Club Master Plan. More information will be shared as key milestones are achieved. Click on the Titles below for more information.

June 24, 2025

Pool House Slab, Steel and Retaining Wall

Pool House Slab, Steel and Retaining Wall

June 17, 2025

Clubhouse Steel, Backfill, Decking, & Poolhouse

Clubhouse Steel, Clubhouse Backfill, Clubhouse Decking, Retaining Wall and Poolhouse

June 09, 2025

Clubhouse Steel, Pool, Poolhouse & Retaining Walls

Clubhouse Steel, Pool Underground, Poolhouse Rough Ins, Retaining Walls and Clubhouse Backfill.

June 03, 2025

Pool House Rough Ins, Steel Progress & Retaining Wall

Pool House Rough Ins, Steel Progress and Retaining Wall.

May 27, 2025

Cart Storage, Steel & Poolhouse Trench

Cart Storage, Steel and Poolhouse Trench.

May 20, 2025

Waterproofing, CMU, Poured Walls & Wall Forms

Clubhouse Wall Waterproofing​, CMU Grout, Poured Walls, Wall Forms, and Poolhouse CMU.